High speed door installation step one: Get ready.


1, materials: special fixtures, scrapers, powder wire bags, impact drills, hand-held electric drills, welding machines, cutting machines, screwdrivers, hammers, wire drops, horizontal rulers and so on.


2, tools: mid-pillar, cover, reel, blade, rail.


Warm tip: the above materials are the installation of fast curtain door necessary tools, the same can not be less, to be ready to start well.


High speed door installation step 2: Start installing the shutter door.


1, determine the location to install the shutter door, and with the wire drop, horizontal ruler and other tools to label, find the right horizontal and vertical lines.


2, according to the positioning of the dash to start the installation of the border of the shutter door.


3, according to the manual instructions of the door machine prompted by the method steps and precautions for the installation of the shutter door machine.


4, the assembled high speed pvc curtain door body fixed, and then the limiter to find the right position installed, and try to run.


5, the runway, manual mechanism, the installation of the bag.


High speed door installation step 3: inspection results.


1, The Asahi peak quick curtain door debugging and operation, to ensure that each function and equipment running well.


2, all installed and checked, the installation of the curtain door even if completed, then can be used normally.